A project manager is leading a project with a total of 6 key stakeholders. To understand the potential complexity of the project's communication, the project manager calculates the number of potential communication channels. How many communication channels exist in this project?
The correct answer is 15. The number of potential communication channels is calculated using the formula N(N-1)/2, where N is the number of stakeholders. In this case, with N = 6, the calculation is 6(6-1)/2 = 6(5)/2 = 30/2 = 15. The other options represent common miscalculations. '30' results from forgetting to divide by two. '21' is the result for 7 stakeholders. '5' is simply the result of N-1. Understanding this formula is crucial for project managers to appreciate how communication complexity increases as more stakeholders are added to a project.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Why is the formula for communication channels N(N-1)/2?
Open an interactive chat with Bash
What happens to communication complexity as more stakeholders are added?
Open an interactive chat with Bash
How can project managers effectively manage increasing communication channels?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .