Project Management Professional Practice Question

A project manager is leading a medical device development project that is subject to stringent health and safety regulations. During planning, stakeholders requested a clear method for tracking adherence to these rules throughout the project lifecycle. What should the project manager do first to address this request to measure compliance?

  • Schedule recurring meetings with the legal department to discuss potential compliance threats.

  • Procure a third-party auditing firm to conduct a compliance review before project launch.

  • Assign a team member to manually check all compliance-related tasks upon completion.

  • Establish key performance indicators (KPIs) and metrics that form a compliance measurement system.

Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot