Project Management Professional Practice Question

A project manager is leading a high-stakes product launch. During the planning phase, they facilitate a workshop to compare a traditional waterfall delivery against an iterative, phased approach. What is the primary purpose of evaluating these distinct delivery options?

  • To select the approach that best aligns with the project's business case and maximizes value delivery to stakeholders

  • To establish a definitive project scope that can be used to create a fixed-price contract with suppliers

  • To accommodate the development team's preferred methodology and optimize their workflow

  • To determine which approach presents the lowest initial project cost and most predictable budget

Project Management Professional
Business Environment
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot