PMI Project Management Professional Practice Question

A project manager is leading a high-risk, cross-functional project within an organization that has a well-established, centralized governance framework. Which of the following would be the most appropriate approach for the project manager to take when determining the project's governance structure?

  • Implement a completely autonomous governance structure that allows the project team to make decisions without external oversight

  • Replicate the organization's centralized governance structure without any modifications for the project

  • Align the project's governance structure with the organization's centralized governance framework while incorporating additional oversight measures to address the project's high-risk nature

  • Establish a project-specific governance structure that operates independently from the organization's governance framework

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot