Project Management Professional Practice Question

A project manager is leading a complex software development project where several team members lack experience with a new programming language required for key tasks. The project sponsor is concerned about upfront costs and suggests that training should only be arranged if the team struggles during the execution phase. What is the project manager's best course of action?

  • Proceed with the project and arrange for just-in-time training during the execution phase only as skill-gap issues arise.

  • Explain to the sponsor that investing in training during the planning phase is essential for mitigating risks, preventing delays, and ensuring quality.

  • Replace the inexperienced team members with external contractors who already possess the required skills.

  • Agree with the sponsor to defer training costs, as this aligns with minimizing the initial project budget.

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot