Project Management Professional Practice Question

A project manager is initiating a high-stakes project involving cross-functional team members from disparate regions. To ensure a high standard of communication, which action is most appropriate for effectively establishing and maintaining adherence to team ground rules during the project kickoff?

  • Implement ground rules without formal announcement, expecting team members to adhere through observation of others.

  • Send an email detailing the ground rules after the kickoff meeting.

  • Delegate to team leaders to convey these ground rules to their subordinates to streamline communication.

  • Formally document and present the ground rules in the kickoff meeting, ensuring all members receive the same information.

Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot