PMI Project Management Professional Practice Question
A project manager is in the process of obtaining resources for a new project. What is the BEST way to ensure the selection of the appropriate resources while taking into account availability, cost, and team member skill sets?
Utilize the project team's past preferences for resource selection
Selecting resources based on the shortest estimated delivery time to speed up the project
Choosing resources based on the lowest quoted cost
Multi-criteria decision analysis to evaluate resources based on predefined criteria