Project Management Professional Practice Question

A project manager is in the process of developing a detailed project schedule. They have already defined the project activities, sequenced them, and estimated their durations. To convert these durations into a timeline with specific start and end dates, which document must they consult to understand the available working days and shifts for the project as a whole?

  • Project calendar

  • Work Breakdown Structure (WBS)

  • Resource calendar

  • Activity list

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot