Project Management Professional Practice Question

A project manager is in the process of defining the project's critical information requirements, which includes the type, format, and frequency of information needed for decision-making and stakeholder updates. Which of the following represents the most effective approach for the project manager to take?

  • Facilitate a requirements-gathering workshop with key project stakeholders.

  • Delegate the task to the lead business analyst and review their findings before implementation.

  • Use the information requirements from a similar, recently completed project to save time and effort.

  • Define the requirements alone to ensure a single, unified vision and prevent conflicting inputs.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot