Project Management Professional Practice Question

A project manager is finalizing the schedule for a critical project. They discover that an unrelated project within the same company requires exclusive use of the primary integration test environment during the same period their team has planned for crucial integration testing. What should be the project manager's first course of action?

  • Immediately escalate the resource conflict to the project sponsor to prioritize their project's access.

  • Proceed with the original schedule, assuming their project has priority over an unrelated one.

  • Collaborate with the other project manager to deconflict the schedules or find a way to share the environment.

  • Request additional budget to procure a separate, dedicated test environment for their project.

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot