A project manager is facing resource constraints and needs to adjust the project schedule without changing the project duration. Which technique should they employ?
Resource smoothing is the correct technique to use in this scenario. Unlike resource leveling, which can extend the project timeline, resource smoothing aims to balance resource usage within the existing project constraints. It adjusts activities within their available float without changing the project end date. This technique is particularly useful when there are fixed deadlines or when the project duration cannot be extended. Resource smoothing helps optimize resource allocation and reduce peaks and valleys in resource utilization while maintaining the original project timeline.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is resource smoothing and how does it work?
Open an interactive chat with Bash
How does resource leveling differ from resource smoothing?
Open an interactive chat with Bash
What are some practical examples of when to use resource smoothing?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access