Project Management Professional Practice Question

A project manager is facilitating the Manage Team process and notices growing tension between two senior developers over the implementation of a complex feature. After mediating a discussion, they agree on a hybrid approach that satisfies both of their technical concerns. What is a primary outcome of the project manager effectively resolving this conflict?

  • Simplification of the project's scope

  • A decreased need for future project documentation

  • Enhanced team productivity and positive working relationships

  • Reduced project management overhead costs

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot