A project manager is evaluating various events and conditions with potential positive impacts on the project objectives. Which strategies should the project manager consider for these identified opportunities?
For identified opportunities, which are events or conditions that can have a positive impact on project objectives if they occur, a project manager can consider five strategies: 'Exploit', 'Share', 'Enhance', 'Accept', and 'Escalate'. 'Exploit' strategies involve taking action to ensure that an opportunity occurs. 'Share' involves allocating some or all of the ownership of the opportunity to a third party who can capture the benefit for the project. 'Enhance' strategies are actions that increase the probability and/or the positive impacts of an opportunity. 'Accept' means being willing to take advantage of the opportunity if it arises, but not actively pursuing it. 'Escalate' is used when the opportunity requires a decision or action at a higher organizational level.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the difference between 'Exploit' and 'Enhance' as opportunity strategies?
Open an interactive chat with Bash
When should a project manager escalate an opportunity?
Open an interactive chat with Bash
How does 'Share' differ from other opportunity strategies?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .