PMI Project Management Professional Practice Question
A project manager is evaluating various events and conditions with potential positive impacts on the project objectives. Which strategies should the project manager consider for these identified opportunities?
Exploit, Share, Enhance, Accept, Escalate
Mitigate, Enhance, Share, Accept, Analyze
Avoid, Transfer, Mitigate, Accept, Escalate
Transfer, Exploit, Ignore, Enhance, Accept