A project manager is evaluating various events and conditions with potential positive impacts on the project objectives. Which strategies should the project manager consider for these identified opportunities?
Mitigate, Enhance, Share, Accept, Analyze
Exploit, Share, Enhance, Accept, Escalate
Transfer, Exploit, Ignore, Enhance, Accept
Avoid, Transfer, Mitigate, Accept, Escalate