Free PMI Project Management Professional Practice Question

A project manager is evaluating two potential projects. Project A has a Benefit-Cost Ratio (BCR) of 1.2, while Project B has a BCR of 0.9. Based on this information, which statement is correct?

  • Project A is financially more attractive

  • Project B is financially more attractive

  • Neither project should be considered

  • Both projects are equally attractive

This question's topic:
PMI Project Management Professional / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.