PMI Project Management Professional Practice Question
A project manager is evaluating the cost performance of a project and has the following data: Budget at Completion (BAC) is $200,000 and the Cost Performance Index (CPI) is 0.8. Using the formula EAC = BAC / CPI, what is the Estimate at Completion (EAC) for the project?
$200,000
$220,000
$250,000
$160,000