PMI Project Management Professional Practice Question

A project manager is evaluating the cost performance of a project and has the following data: Budget at Completion (BAC) is $200,000 and the Cost Performance Index (CPI) is 0.8. Using the formula EAC = BAC / CPI, what is the Estimate at Completion (EAC) for the project?

  • $220,000

  • $250,000

  • $160,000

  • $200,000

PMI Project Management Professional
People
Your Score:
Settings & Objectives

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot