PMI Project Management Professional Practice Question

A project manager is evaluating the cost performance of a project and has the following data: Budget at Completion (BAC) is $200,000 and the Cost Performance Index (CPI) is 0.8. Using the formula EAC = BAC / CPI, what is the Estimate at Completion (EAC) for the project?

  • $220,000

  • $160,000

  • $250,000

  • $200,000

PMI Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot