PMI Project Management Professional Practice Question

A project manager is estimating the duration of a task with the following data: Optimistic time = 8 days, Most Likely time = 12 days, and Pessimistic time = 20 days. The Expected Duration (TE) of the task is 15 days.

  • False

  • True

PMI Project Management Professional
People
Your Score:
Settings & Objectives

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot