PMI Project Management Professional Practice Question
A project manager is estimating the duration of a task using PERT. The optimistic estimate for the task is 8 days, the most likely estimate is 12 days, and the pessimistic estimate is 20 days. What is the standard deviation of the task's duration?
2 days
4 days
6 days
8 days