PMI Project Management Professional Practice Question

A project manager is discussing risk management with the team. Which of the following statements best reflects an iterative approach to assessing and prioritizing risks?

  • Risks should be thoroughly assessed during the project planning phase and then reviewed at each major milestone.

  • The team should conduct a comprehensive risk assessment at the beginning of the project and then monitor for risk events throughout the project.

  • The team should assess and prioritize risks whenever a potential risk event is identified, focusing on addressing each risk individually.

  • Risks should be continuously assessed and prioritized, with the risk register updated regularly to reflect changes in the project environment.

PMI Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot