Free PMI Project Management Professional Practice Question

A project manager is developing a Risk Management Plan for a new project. Which of the following BEST describes the primary purpose of the Risk Management Plan?

  • To outline the specific risk responses for identified threats and opportunities

  • To document the risk threshold and risk appetite of all project stakeholders

  • To ensure that the degree, type, and visibility of risk management are proportionate to both the risks and the importance of the project to the organization and stakeholders

  • To assign risk owners to all identified risks and create a risk mitigation plan

This question's topic:
PMI Project Management Professional / 
Process
Your Score:

Check or uncheck an objective to set which questions you will receive.