Project Management Professional Practice Question

A project manager is developing a project schedule using the Precedence Diagramming Method (PDM). An activity within the schedule has a calculated Late Start (LS) of day 22 and a duration of 5 days. What is the Late Finish (LF) for this activity?

  • Day 26

  • Day 28

  • Day 27

  • Day 17

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot