A project manager is developing a project schedule using the Precedence Diagramming Method (PDM). An activity within the schedule has a calculated Late Start (LS) of day 22 and a duration of 5 days. What is the Late Finish (LF) for this activity?
The correct answer is day 27. The formula for calculating the Late Finish (LF) in the Critical Path Method is: LF = Late Start (LS) + Duration. In this scenario, LF = 22 + 5 = 27. This calculation is a core component of the backward pass analysis in schedule network diagramming and is crucial for determining the project's critical path and the float of individual activities. The other answers are based on incorrect calculations, such as subtracting one day from the total (22 + 5 - 1 = 26), which is a common mistake based on an alternative but less standard counting convention.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the difference between Late Start (LS) and Late Finish (LF)?
Open an interactive chat with Bash
What is backward pass analysis in project scheduling?
Open an interactive chat with Bash
What is 'float' and how is it calculated in project schedules?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .