PMI Project Management Professional Practice Question

A project manager is currently in the process of monitoring and controlling a large construction project. Unexpected weather conditions have caused significant delays, and work performance data indicates that the project will not meet its original timelines. Which of the following actions should the project manager take in accordance to the project management best practices for managing these kinds of situation?

  • Update the project management plan to reflect the revised project schedule, incorporating the delays and proposing new timelines.

  • Inform the stakeholders about the delay, continue with the original project management plan.

  • Do not take any action as the environmental conditions are beyond the control of the project team.

  • Reduce the project scope to meet the original deadline.

PMI Project Management Professional
Waterfall
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot