A project manager is calculating the Planned Value (PV) for a construction project. The project has a Budget at Completion (BAC) of $500,000 and is expected to be 30% complete by the end of the current month. What is the Planned Value (PV) for this project?

  • $350,000

  • $150,000

  • $166,667

  • $133,333