A project manager is calculating the Planned Value (PV) for a construction project. The project has a Budget at Completion (BAC) of $500,000 and is expected to be 30% complete by the end of the current month. What is the Planned Value (PV) for this project?
$350,000
$150,000
$166,667
$133,333