PMI Project Management Professional Practice Question

A project manager is assessing risks for a new software development project. Risk A has a probability of 0.4 and an impact of 0.5, while Risk B has a probability of 0.6 and an impact of 0.3. Which risk should the project manager prioritize?

  • Risk B

  • The risk with the highest probability

  • Risk A

  • Both risks equally