Project Management Professional Practice Question

A project manager has been emailing weekly status reports to the project's stakeholders. At a steering-committee meeting, several participants admit they did not understand the impact of a recently announced schedule change. To follow PMI best practices for managing communications, what should the project manager do to ensure future messages are correctly understood?

  • Post updates on a shared drive and trust stakeholders to review them

  • Ask stakeholders for feedback and confirmation that they understand the information

  • Add more detailed technical terminology to demonstrate expertise

  • Continue sending weekly email status reports without change

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot