A project manager calculates the Schedule Performance Index (SPI) and finds it to be 0.85. What does this value indicate about the project's schedule performance?
The correct answer is that the project is behind schedule. The Schedule Performance Index (SPI) is a measure of schedule efficiency in Earned Value Management. It is calculated by dividing the Earned Value (EV) by the Planned Value (PV). An SPI of 1.0 indicates the project is exactly on schedule. When SPI is less than 1.0, it means the project is behind schedule. In this case, an SPI of 0.85 indicates that the project has only completed 85% of the work that was planned to be completed by this point in time. This suggests the project is running behind its planned schedule and may require corrective actions to get back on track. Conversely, an SPI greater than 1.0 would indicate the project is ahead of schedule.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is the Schedule Performance Index (SPI)?
Open an interactive chat with Bash
What is Earned Value Management (EVM)?
Open an interactive chat with Bash
Why is it important to monitor schedule performance?
Open an interactive chat with Bash
Project Management Professional
Process
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access