A project manager at an IT firm is nearing the completion phase of a project aimed at reducing the processing time of customer service requests. The initial project plan outlined significant benefits in the form of reduced processing times and increased customer satisfaction. Which of the following would BEST ensure that the project has a reliable system in place to track these projected benefits post-deployment?
Conduct a series of stakeholder meetings to discuss the benefits of the project
Design a user survey to gather qualitative feedback about the new system's usability
Review the original project charter to assess if the stated benefits align with the project's outcomes
Implement a set of key performance indicators (KPIs) that measure processing times and customer satisfaction rates
For tracking the projected benefits accurately, it's crucial to set up key performance indicators (KPIs) that are directly aligned with the objectives, such as reduced processing times and improved customer satisfaction rates. The other options, while potentially useful in other contexts, do not directly ensure a system is in place to measure the specific benefits that the project aimed to achieve.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are key performance indicators (KPIs)?
Open an interactive chat with Bash
How do KPIs relate to project outcomes?
Open an interactive chat with Bash
What methods can be used to implement KPIs effectively?
Open an interactive chat with Bash
Project Management Professional
Business Environment
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access