Project Management Professional Practice Question

A project is underway when a key stakeholder requests an additional feature, extending the duration of a critical path task by two weeks. The project manager must evaluate the request and take necessary actions to manage the change. What should the project manager do FIRST in response to this situation?

  • You selected this option

    Reject the change request to maintain the original schedule and prevent any delays.

  • You selected this option

    Inform the stakeholder that changes cannot be made to tasks on the critical path when following the Waterfall Methodology.

  • You selected this option

    Evaluate the impact of the new feature on the project's schedule baseline and overall objectives.

  • You selected this option

    Approve the change request to accommodate the stakeholder's need.

Project Management Professional
Waterfall
Your Score:
Settings & Objectives
N/A
N/A
N/A
N/A
N/A
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot