Project Management Professional Practice Question

A project has a Budget at Completion (BAC) of $800,000. The cumulative Cost Performance Index (CPI) is 0.90, and you believe this cost performance trend will continue for the remainder of the work. Using the earned value formula EAC = BAC / CPI, what is the project's Estimate at Completion (EAC)?

  • $1,005,000

  • $800,000

  • $888,889

  • $720,000

Project Management Professional
Process
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot