PMI Project Management Professional Practice Question
A project has a Budget at Completion (BAC) of $500,000. The project has spent $200,000 to date (AC) and has realized an Earned Value (EV) of $160,000. If the project management intends to meet the original budget goals, what is the To-Complete Performance Index (TCPI)?
1.25
1.00
1.13
0.80