PMI Project Management Professional Practice Question

A project has a Budget at Completion (BAC) of $500,000. The Earned Value (EV) is calculated at $200,000, while the Actual Cost (AC) has reached $250,000. Using the BAC-based formula, what is the To-Complete Performance Index (TCPI) that will help the project meet its planned budget?

  • 1.2

  • 1.0

  • 0.8

  • 1.5

PMI Project Management Professional
People
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot