PMI Project Management Professional Practice Question
A project has a Budget at Completion (BAC) of $500,000. The Earned Value (EV) is calculated at $200,000, while the Actual Cost (AC) has reached $250,000. Using the BAC-based formula, what is the To-Complete Performance Index (TCPI) that will help the project meet its planned budget?
1.0
0.8
1.2
1.5