PMI Project Management Professional Practice Question

A project has a Budget at Completion (BAC) of $500,000. The Earned Value (EV) is calculated at $200,000, while the Actual Cost (AC) has reached $250,000. Using the BAC-based formula, what is the To-Complete Performance Index (TCPI) that will help the project meet its planned budget?

  • 1.0

  • 0.8

  • 1.2

  • 1.5

PMI Project Management Professional
People
Your Score:
Settings & Objectives

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot