Free PMI Project Management Professional Practice Question

A project has a Budget at Completion (BAC) of $500,000. The actual cost incurred so far is $200,000, and the Earned Value (EV) is calculated to be $250,000. What is the Cost Performance Index (CPI) for this project?

  • 0.80

  • 1.10

  • 2.00

  • 1.25

This question's topic:
PMI Project Management Professional / 
People
Your Score:

Check or uncheck an objective to set which questions you will receive.