PMI Project Management Professional Practice Question
A project activity has an Early Start (ES) of Day 5 and a Late Start (LS) of Day 8. What is the total float for this activity?
2 days
8 days
5 days
3 days
A project activity has an Early Start (ES) of Day 5 and a Late Start (LS) of Day 8. What is the total float for this activity?
2 days
8 days
5 days
3 days
The correct answer is 3 days. Float, also known as slack, is the amount of time an activity can be delayed without impacting the project's overall schedule. It can be calculated using two formulas:
In this case, we are given the Early Start (ES) and Late Start (LS) values. Using the first formula:
Float = LS - ES Float = 8 - 5 Float = 3 days
This means the activity can be delayed by up to 3 days without affecting the project's critical path or end date. Understanding float is essential for project managers to prioritize tasks, allocate resources efficiently, and manage schedule risks.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
Join premium for unlimited access and more features
All plans include the following perks.
Our pricing is simple. Full access to all certifications and exams, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
No annoying ads and popups. Study without distractions.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even more discounts than before.
Unlimited access to all PBQs and be prepared for the real thing.
Create an account or sign in to access our study materials.