You are managing a software development project when a team member alerts you to a potential risk: a new regulatory change could require significant alterations to your project's deliverables. What is the most appropriate action to take regarding this information?
Inform the project sponsor for further guidance
Do not address the risk at this moment
Record the risk in the risk register along with potential responses
Modify the project scope to include the regulatory change