CAPM Practice Question

You are managing a software development project when a team member alerts you to a potential risk: a new regulatory change could require significant alterations to your project's deliverables. What is the most appropriate action to take regarding this information?

  • Inform the project sponsor for further guidance

  • Do not address the risk at this moment

  • Record the risk in the risk register along with potential responses

  • Modify the project scope to include the regulatory change

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot