CAPM Practice Question

You are managing a project with tight deadlines. A key stakeholder suggests adding unverified data to a report to make the project's progress look better to upper management. What is the most appropriate action for you to take according to the PMI Code of Ethics and Professional Conduct?

  • Agree to include the unverified data to satisfy the stakeholder.

  • Explain that only verified information can be included in the report.

  • Ignore the stakeholder's suggestion and proceed without addressing it.

  • Report the stakeholder's suggestion to upper management immediately.

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot