CAPM Practice Question

You are managing a project with a total budget (Budget at Completion) of $150,000 and a planned duration of 6 months. At the end of the 3rd month, the project has incurred actual costs (AC) of $90,000. According to the project plan, 50% of the work should be completed by now, but only 40% is actually completed. What are the cost variance (CV) and schedule variance (SV) for the project at this point?

  • Cost Variance is -$30,000; Schedule Variance is -$15,000

  • Cost Variance is $30,000; Schedule Variance is $15,000

  • Cost Variance is -$15,000; Schedule Variance is -$30,000

  • Cost Variance is $15,000; Schedule Variance is $30,000

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot