CAPM Practice Question
You are developing a project schedule and need to represent the completion of the 'Design Phase' without adding any duration to the timeline. Which of the following is the most appropriate way to include this in your project plan?
Schedule a meeting with the team to discuss the phase outcome
Mark it with a milestone indicating a significant point in the schedule
Add a task representing the completion with a minimal duration
Insert a delay period to signify the phase completion