CAPM Practice Question

You are developing a project schedule and need to represent the completion of the 'Design Phase' without adding any duration to the timeline. Which of the following is the most appropriate way to include this in your project plan?

  • Schedule a meeting with the team to discuss the phase outcome

  • Mark it with a milestone indicating a significant point in the schedule

  • Add a task representing the completion with a minimal duration

  • Insert a delay period to signify the phase completion

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot