You are assigned as the project manager for a project that has clear objectives, well-understood requirements, and a fixed budget and timeline. The project scope is unlikely to change, and stakeholders have agreed on the deliverables. Which project management methodology is most suitable for managing this project?

  • Employ a flexible, change-driven approach.

  • Implement a hybrid approach combining predictive and adaptive techniques.

  • Use a traditional waterfall methodology.

  • Adopt an agile methodology focused on iterative development.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot