You are assigned as the project manager for a project that has clear objectives, well-understood requirements, and a fixed budget and timeline. The project scope is unlikely to change, and stakeholders have agreed on the deliverables. Which project management methodology is most suitable for managing this project?
Employ a flexible, change-driven approach.
Implement a hybrid approach combining predictive and adaptive techniques.
Use a traditional waterfall methodology.
Adopt an agile methodology focused on iterative development.