CAPM Practice Question
While developing the project schedule for a website redesign, you identify the go-live date as a significant point in the timeline. To highlight this key moment without allocating time for work, how should you represent it in your project schedule?
Exclude it from the schedule since it doesn't involve actual work.
Represent it as a summary activity that includes all preceding tasks.
Represent it as a task with a specified duration to plan the work involved.
Represent it as a milestone to mark the significant event without duration.