Which statement correctly distinguishes a milestone from a regular activity in a project schedule?

  • A milestone requires additional resources and is always the longest activity in the schedule.

  • A milestone can only be assigned to activities on the critical path and must have positive float.

  • A milestone is a recurring task that consumes budget and labor hours throughout the project.

  • A milestone has zero duration and represents a significant event or decision point in the project.

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot