CAPM Practice Question
Which scheduling method identifies the sequence of activities that determines the minimum project completion time?
Critical Path Method
Monte Carlo Simulation
Resource Leveling
Rolling Wave Planning
Which scheduling method identifies the sequence of activities that determines the minimum project completion time?
Critical Path Method
Monte Carlo Simulation
Resource Leveling
Rolling Wave Planning
The Critical Path Method identifies the longest sequence of tasks that must be completed on time for the project to be finished by its due date. This sequence determines the shortest possible project duration because any delay in these tasks will delay the entire project.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.