Which project management tool helps ensure that requirements are tracked throughout the project lifecycle, linking each requirement to its origin and verifying that the final deliverables meet the initial requirements?
The Requirements Traceability Matrix (RTM) is used to link requirements to their origins and track them throughout the project lifecycle. It ensures that all requirements are addressed in the final product and that none are overlooked. The RTM helps in verifying that each requirement has been fulfilled by the deliverables. Other options serve different purposes: a Gantt Chart is used for scheduling tasks, the Work Breakdown Structure breaks the project into manageable sections, and an Issue Log tracks problems encountered during the project.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
How does the Requirements Traceability Matrix (RTM) ensure no requirements are overlooked?
Open an interactive chat with Bash
What are the differences between a Gantt Chart and a Requirements Traceability Matrix?
Open an interactive chat with Bash
Can you explain the primary benefits of using a Requirements Traceability Matrix in a project?
Open an interactive chat with Bash
CAPM
Business Analysis Frameworks
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .