CAPM Practice Question
Which project management document provides a hierarchical decomposition of the project scope into deliverables and work packages?
Scope Statement
Project Schedule
Work Breakdown Structure
Risk Register
Which project management document provides a hierarchical decomposition of the project scope into deliverables and work packages?
Scope Statement
Project Schedule
Work Breakdown Structure
Risk Register
The Work Breakdown Structure (WBS) is the document that provides a hierarchical decomposition of the project's total scope into smaller, manageable components called deliverables and work packages. It helps in organizing and defining the total work of the project. The Project Schedule outlines timelines, the Risk Register lists potential risks, and the Scope Statement defines the project's scope but does not break it down into hierarchical components.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.