Which project element represents an important point in the project timeline but does not have duration or require resources?
A work package
A task
A project phase
A milestone
Which project element represents an important point in the project timeline but does not have duration or require resources?
A work package
A task
A project phase
A milestone
A milestone represents a significant point or event in a project schedule without any duration or resource allocation. It is used to mark the completion of key activities, deliverables, or phases. In contrast, a task and a work package involve work that consumes time and resources. A project phase encompasses a group of related tasks and also has a duration.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.