Which project document outlines a hierarchical decomposition of the project's deliverables and work to be executed by the team?
Project Charter
Work Breakdown Structure
Requirements Traceability Matrix
Scope Statement
Which project document outlines a hierarchical decomposition of the project's deliverables and work to be executed by the team?
Project Charter
Work Breakdown Structure
Requirements Traceability Matrix
Scope Statement
The Work Breakdown Structure (WBS) is a key project management tool that breaks down the project's total scope into manageable sections, representing a hierarchical decomposition of the work to be performed. This helps in organizing and defining the total scope of the project. Other documents like the Project Charter provide a high-level overview, the Requirements Traceability Matrix links requirements to their origins, and the Scope Statement details the project's scope but does not provide a hierarchical breakdown.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.