The correct statement is that the critical path is the longest sequence of dependent tasks, and it determines the shortest possible project duration. Any delay to an activity on the critical path will delay the entire project's completion. The critical path is characterized by having zero total float. The other options are incorrect: the shortest path is not the critical path, flexibility (float) is minimal or non-existent on the critical path, and while critical path activities can be high-risk or expensive, the path itself is defined strictly by duration and dependencies.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is total float in the context of the critical path?
Open an interactive chat with Bash
How does the critical path impact project management decisions?
Open an interactive chat with Bash
What tools are used to calculate the critical path in a project?
Open an interactive chat with Bash
CAPM
Predictive, Plan-Based Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .