CAPM Practice Question
Which of the following outputs is produced during the project initiation phase and formally authorizes a project to begin?
Project charter
Risk response plan
Cost baseline
Detailed project schedule
Which of the following outputs is produced during the project initiation phase and formally authorizes a project to begin?
Project charter
Risk response plan
Cost baseline
Detailed project schedule
The project charter is the primary output of the initiating process group. It formally authorizes the project, names the project manager, and records the project's purpose, objectives, high-level requirements, and success criteria. Detailed documents such as the comprehensive project schedule, cost baseline, and risk response plan are produced later in the planning phase once the charter has been approved.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.