CAPM Practice Question
Which of the following is an example of a project management artifact used to document project controls in a predictive, plan-based project?
Change Control Log
Product Backlog
Burndown Chart
Daily Stand-up Meeting Notes
Which of the following is an example of a project management artifact used to document project controls in a predictive, plan-based project?
Change Control Log
Product Backlog
Burndown Chart
Daily Stand-up Meeting Notes
A Change Control Log is a key artifact in predictive, plan-based projects used to document and track all changes to the project scope, schedule, and costs. It helps in maintaining control over the project by providing a record of all requested and approved changes. Other options like Product Backlogs, Burndown Charts, and Daily Stand-up Meeting Notes are typically associated with Agile methodologies.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams.
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.