Which of the following is a primary artifact used in adaptive project management methodologies to prioritize and manage work items throughout the development process?
The Product Backlog is a key artifact in adaptive methodologies like Scrum. It is an ordered list of everything that is known to be needed in the product and serves as the single source of requirements. The Product Backlog evolves as the product and its environment do. The Work Breakdown Structure and Gantt Chart are tools typically used in predictive, plan-based projects, not adaptive ones. Critical Path Analysis is a technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility; it is also more common in traditional project management approaches.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a Product Backlog in adaptive project management?
Open an interactive chat with Bash
How is a Product Backlog different from a Work Breakdown Structure?
Open an interactive chat with Bash
Who is responsible for managing the Product Backlog?
Open an interactive chat with Bash
CAPM
Agile Frameworks/Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Pass with Confidence.
Project Management Package
You have hit the limits of our free tier, become a Premium Member today for unlimited access.
Military, Healthcare worker, Gov. employee or Teacher? See if you qualify for a Community Discount.
Monthly
$9.99
$9.99/mo
Billed monthly, Cancel any time.
3 Month Pass
$19.99
$6.66/mo
One time purchase of $19.99, Does not auto-renew.
BEST DEAL
Lifetime Pass
$29.99
One time purchase, Good for life.
What You Get
All Project Management Package plans include the following perks and exams .